Application of earned value based metrics on small-scale construction projects

  • Radoslav Avlijaš Singidunum University
  • Goran Avlijaš Singidunum University
  • Milenko Heleta Singidunum University

Abstract


The application of earned value based metrics in Serbia lags significantly behind other developed economies, regardless of the fact that is has proven to be a very useful and flexible tool for prediction of total cost and time of construction projects. This paper aims to contribute to the wider use of earned value management (EVM) as a practical metrics that can be used to track performance of small-scale construction projects. Literature review reveals how the method evolved as a fundamental tool for construction projects monitoring and refers to specific issues concerning its implementation. In order to enable practitioners to realize all advantages of earned value based performance monitoring of small-scale construction projects, the applicability of such methodology is demonstrated through a case study.

References

Assaf, S.A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349-357. doi:10.1016/j.ijproman.2005.11.010.

Avlijaš, R., & Avlijaš, G. (2010). Upravljanje projektom. Beograd: Univerzitet Singidunum. In Serbian.

Christensen, D.S., & Templin, C. (2002). EAC evaluation methods: do they still work. Acquisition Review Quarterly, 9, 105-116.

Christensen, D.S. (1998). Cost and benefits of earned value management process. Acquisition Review Quarterly, 5, 372-386.

Christensen, D.S. (1999). Using the earned value cost management report to evaluate the contractor’s estimate at completion. Acquisition Review Quarterly, 19, 283-296.

Christensen, D.S., & Heise, S. (1993). Cost performance index stability. National Contract Management Journal, 25, 7-15.

Colin, J., & Vanhoucke, M. (2014). Setting tolerance limits for statistical project control using earned value management. Omega, 49, 107-122. doi:10.1016/j.omega.2014.06.001.

De Marco, A., & Narbaev, T. (2013). Earned value-based performance monitoring of facility construction projects. Journal of Facilities Management, 11(1), 69-80. doi:10.1108/14725961311301475.

Doloi, H., Sawhney, A., Iyer, K.C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), 479-489. doi:10.1016/j.ijproman.2005.11.010.

Fleming, Q.W., & Koppelman, J.M. (2003). What’s your project’s real price tag. Harvard Business Review, 20-21. doi:10.1225/F0309C.

Flyvbjerg, B., Holm, M.S., & Buhl, S. (2002). Underestimating costs in public works projects: Error or lie. Journal of the American Planning Association, 68(3), 279-295. doi:10.1080/01944360208976273.

Kim, E., Wells, W.G., & Duffey, M.R. (2003). A model for effective implementation of Earned Value Management methodology. International Journal of Project Management, 21(5), 375-382. doi:10.1016/j.ijproman.2005.11.010.

Kwak, Y.H., & Anbari, F.T. (2012). History, practices, and future of earned value management in government: Perspectives from NASA. Project Management Journal, 43(1), 77-90. doi:10.1002/pmj.20272.

Lipke, W. (2003). Schedule is different. Retrieved Jun 21, 2015, from http://www.earnedschedule.com/Docs/Schedule%20is%20Different.pdf

Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400-407. doi:10.1016/j.ijproman.2008.02.009.

Mladenović, I. (2013). Građevinarstvo kao industrijski sektor u funkciji oporavka privrede Republike Srbije. Ekonomski horizonti, 15(3), 245-256. doi:10.5937/ekonhor1303245M

Naeni, L.M., Shadrokh, S., & Salehipour, A. (2011). A fuzzy approach for the earned value management. International Journal of Project Management, 29(6), 764-772. doi:10.1016/j.ijproman.2008.02.009.

Narbaev, T., & De Marco, A. (2014). An earned schedule-based regression model to improve cost estimate at completion. International Journal of Project Management, 32(6), 1007-1018. doi:10.1016/j.ijproman.2008.02.009.

Project Management Institute. (2011). Practice standard for earned value management. Newtown Square, PA: Project Management Institute.

Project Management Institute. (2013). A guide to the project management body of knowledge. Newtown Square, PA: Project Management Institute.

Ponz-Tienda, J.L., Pellicer, E., & Yepes, V. (2012). Complete fuzzy scheduling and fuzzy earned value management in construction projects. Journal of Zhejiang University SCIENCE A: Applied Physics & Engineering, 13(1), 56-68. doi:10.1631/jzus.A1100160.

Russell, S. (2008). Earned value management: uses and misuses. Air Force Journal of Logistics, 32(2), 85-91.

Serbian Chamber of Commerce. (2015). Građevinarstvo, industrija građevinskog materijala i stambena privreda. Retrieved March 20, 2015 from http://www.pks.rs/PrivredaSrbije.aspx?id=7&p=2. In Serbian.

Statistical Office of the Republic of Serbia. (2015). Total value of executed construction works. Retrieved Jun 21, 2015, from http://webrzs.stat.gov.rs/WebSite/

Trbović, A., Vonnegut, A., Brnabić, A., Valentine, S., & Seas, W. (2007). Konkurentni potencijal 11 grana srpske privrede. Ekonomska misao: časopis Saveza Ekonomista Srbije za Pitanja Ekonomske Teorije i Prakse, 40(1-2), 52-66. In Serbian.

Vandevoorde, S., & Vanhoucke, M. (2006). A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24(4), 289-302. doi:10.1016/j.ijproman.2005.10.004.

Wilson, B., Ariyachandra, T., & Frolick, M. (2013). Earned value management systems: Challenges and future direction. Journal of Integrated Enterprise Systems, 2(1), 9-17.

Yang, H., Yeung, J.F.Y., Chan, A.P.C., Chiang, Y.H., & Chan, D.W.M. (2010). A critical review of performance measurement in construction. Journal of Facilities Management, 8(4), 269-284. doi:10.1108/14725961011078981.

Published
2015/10/21
Section
Original Scientific Paper