The Operating Performance Tests of Power Unit A5 in TPP "Kolubara" in Load-Frequency Control

  • Jelena Pavlović Electrical engineering institute Nikola Tesla, University of Belgrade
  • Dane Džepčeski Electrical engineering institute Nikola Tesla, University of Belgrade
  • Vladimir Stanojčić Electrical engineering institute Nikola Tesla, University of Belgrade
  • Dušan Arnautović Electrical engineering institute Nikola Tesla, University of Belgrade
  • Slobodan Bogdanović Electrical engineering institute Nikola Tesla, University of Belgrade
  • Aleksandar Latinović TPP “KOLUBARA"
  • Dušan Duboka TPP “KOLUBARA"

Abstract


As a result of significance of primary frequency control, as well as diversity of turbine-governing systems implementation, their possibilities, parameter settings, various operating conditions, operating modes and duration, there is a need for collection and systematization of data relevant to participation of each power unit in EPS in primary frequency control. In this purpose the turbine governor settings were experimentally determined. The subject of this paper are test results of participation quality of one thermal unit in primary frequency control, and also measurement results of turbine-governing system parameters, on which parameters of mathematical model of turbine governor and thermal power unit as an element of the power system are calculated.

References

UCTE Policy 1:Load-Frequency Control and Performance [C]. Final version, 19. March 2009.

Pravila o radu prenosnog sistema, verzija 1.0, JP EMS, april 2008. god.

Izmene i dopune pravila o radu prenosnog sistema, JP EMS, decembar 2011. god.

IEC 610064 {ed 1.0}b - Acceptance tests for steam turbine speed control systems. First edition, April 1991.

IEC 60045-1{ed 1.0}b - Steam Turbines Specification. First edition, May 1991.