Primena Pareto analize u menadžmentu rizikom otkaza i zastoja buldozera

  • Vesna K Spasojević-Brkić Univerzitet u Beogradu, Mašinski fakultet
  • Martina Perišić University of Belgrade, Faculty of Mechanical Engineering
  • Zorica Veljković University of Belgrade, Faculty of Mechanical Engineering
  • Mirjana Misita University of Belgrade, Faculty of Mechanical Engineering
  • Milanko Damjanović University of Montenegro, Faculty of Mechanical Engineering
Ključne reči: Pareto analiza, buldozer, tip otkaza, frekvencija otkaza, vreme trajanja otkaza, rizik od otkaza

Sažetak


Istraživanja vezana za otkaze i zastoje u radu buldozera veoma su ograničena, te je ova oblast nedovoljno istražena. Cilj ovog rada je da identifikuje sve uzroke otkaza i zastoja buldozera, a potom da izdvoji one najuticajnije. Data je deskriptivna statistika, a zatim i dijagram rasipanja za stepen opasnosti i vremena otkaza i zastoja buldozera i histogrami stepena opasnosti i vremena otkaza i zastoja za buldozere. Potom je data Pareto analiza za tri kategorije: frekvenciju otkaza i zastoja, vreme trajanja otkaza/zastoja i nivoa rizika od otkaza/zastoja. Pareto analiza je pokazala da su sve kod tri kategorije najčešći otkazi/zastoji nastali zbog popravke grejanja, zamene ulja, čišćenja, podešavanja krajnica, zamene filtera, zamene creva i zamene vijaka, te da je neophodno posebnu pažnju obratiti na ove otkaze/zastoje. Корак ка „фабрикама без одржавања“ требало би да укључи планирање идентификованих активности у паузама рада као превентивне, а не корективне активности.

Biografija autora

Vesna K Spasojević-Brkić, Univerzitet u Beogradu, Mašinski fakultet
Prof. dr Vesna Spasojević-Brkić, Katedra za Industrijsko inženjerstvo, Mašinski fakultet Univerziteta u Beogradu

Reference

Akinnuli, B., & Olaleye, J. (2013). An Expert System for Diagnosing and Proffering Solutions to Causes of Overheating in a Bulldozer Engine (Case Study Model D60s-6 Komatsu Products). Engineering Management Research, 2(2), Article 2. https://doi.org/10.5539/emr.v2n2p56


Annie Rose Nirmala, D., Kannan, V., Thanalakshmi, M., Joe Patrick Gnanaraj, S., & Appadurai, M. (2022). Inventory management and control system using ABC and VED analysis. Materials Today: Proceedings, 60, 922–925. https://doi.org/10.1016/j.matpr.2021.10.315


Conger, S. (2015). Six Sigma and Business Process Management. In J. vom Brocke & M. Rosemann (Eds.), Handbook on Business Process Management 1: Introduction, Methods, and Information Systems (pp. 127–146). Springer. https://doi.org/10.1007/978-3-642-45100-3_6


Craft, R. C., & Leake, C. (2002). The Pareto principle in organizational decision making. Management Decision, 40(8), 729–733. https://doi.org/10.1108/00251740210437699


Deulgaonkar, V. R., Karambelkar, A., Kulkarni, A., & Kashid, C. (2021). Failure analysis of Taper-Lock bush used in aggregate batcher plant for construction applications. Engineering Failure Analysis, 130, 105753. https://doi.org/10.1016/j.engfailanal.2021.105753


Duarte, J., Baptista, J. S., & Torres Marques, A. (2019). Occupational Accidents in the Mining Industry—A Short Review. In P. M. Arezes, J. S. Baptista, M. P. Barroso, P. Carneiro, P. Cordeiro, N. Costa, R. B. Melo, A. S. Miguel, & G. Perestrelo (Eds.), Occupational and Environmental Safety and Health (pp. 61–69). Springer International Publishing. https://doi.org/10.1007/978-3-030-14730-3_7


Flores, B. E., & Clay Whybark, D. (1986). Multiple Criteria ABC Analysis. International Journal of Operations & Production Management, 6(3), 38–46. https://doi.org/10.1108/eb054765


Fry, P. R. (2003). Loads and stresses—The real cause of failures in surface mining machinery. Practical Failure Analysis, 3(2), 7–14. https://doi.org/10.1007/BF02717417


Horberry, T., Burgess-Limerick, R., Cooke, T., & Steiner, L. (2016). Improving Mining Equipment Safety Through Human-Centered Design. Ergonomics in Design, 24(3), 29–34. https://doi.org/10.1177/1064804616636299


Kazan, E., & Usmen, M. A. (2018). Worker safety and injury severity analysis of earthmoving equipment accidents. Journal of Safety Research, 65, 73–81. https://doi.org/10.1016/j.jsr.2018.02.008


Misita, M., Spasojević Brkić, V., Brkić, A., Kirin, S., Rakonjac, I., & Damjanović, M. (2021). Impact of downtime pattern on mining machinery efficiency. Structural Integrity and Life, 21(1), 29–35.Accepted: 2022-09-19T19:22:54Z


Misita, M. Ž., Spasojević-Brkić, V. K., Rakonjac, I. M., Damjanović, M. Z., Perišić, M. B., Papić, N. L., & Đurić, G. P. (2022). Dumper operation risk analysis model and HAMRISK expert system. Tehnika, 77(5), 617–624. https://doi.org/10.5937/tehnika2205617M


Spasojević Brkić, V. K., Klarin, M. M., & Brkić, A. Dj. (2015). Ergonomic design of crane cabin interior: The path to improved safety. Safety Science, 73, 43–51. https://doi.org/10.1016/j.ssci.2014.11.010


Spasojević-Brkić, V. K., Veljkovic, Z., Brkic, A., Misita, M., Perisic, M., & Papic, N. (2022). TRANSPORT AND MINING MACHINES OPERATORS’ BEHAVIORAL ATTITUDES IN SAFETY CLIMATE CONTEXT. Journal of Applied Engineering Science, 20(4), Article 4. https://doi.org/10.5937/jaes0-37669


Tanasijevic, M., Jovancic, P., Ivezic, D., Bugaric, U., & Djuric, R. (2019). A FUZZY-BASED DECISION SUPPORT MODEL FOR EFFECTIVENESS EVALUATION – A CASE STUDY OF EXAMINATION OF BULLDOZERS. International Journal of Industrial Engineering: Theory, Applications and Practice, 26(6), Article 6. https://doi.org/10.23055/ijietap.2019.26.6.3304


 

Objavljeno
2023/01/11
Rubrika
Originalni naučni članak